ClientSonic Rail Services Project
ProjectBolt Hole Programme
Duration6 Months
Value£125,000

Project Description

The aim of the project was to provide increased 10-car stabling for the Class 701 vehicle at a number of locations in Wessex as part of the ‘Bolt-Hole’ programme. This included sites at Shepperton, Clapham, Basingstoke and Fareham.

InoRail provided the following services to facilitate the delivery of the scheme;

  • Site surveying; Topographical surveys and detailed inspections
  • Scheme Optioneering (Grip 3)
  • Outline and Detailed PWay and Civil Engineering design
  • Engineering assurance and provision of CRE services