The VolkerRailStoryJV secured the Hope Valley upgrade scheme that will remove bottlenecks on the rail line between Sheffield and Manchester. The scheme is estimated at £137million and will provide;
- An additional track through Dore & Totley Station, this requires a second platform and bridge between the two platforms to allow passengers to board trains on the Hope Valley line to and from Sheffield extending the platform from 115m to 153m
- An extension to the single track which links the Hope Valley line with the Midland Mainline to the west of Dore & Totley Station, which is used mainly by freight services
- Construct a 1km passing loop alongside the existing railway to the east of Bamford station for passenger trains to overtake slower freight trains.
- A new footbridge to the west of Hathersage station to replace an existing railway crossing
Key project milestones are scheduled as follows
- Survey Work – April to October 2021
- Site Establishment – Autumn/ Winter 2021
- Construction Works – begins early 2022
- Project Complete – Summer 2023
InoRail Ltd are contracted to provide all surveying services to support Grip 4 and Grip 5 design phases, this includes;
- Establishment of a route wide Primary and Secondary Control network, between Manchester and Sheffield
- Tertiary Control installation at intervention locations
- Detailed Topographical Surveys
- Route scan, utilising the GEDO Scan system
- Static scanning of all Overbridges and Culverts
- Platform and Structure gauging surveys
- Utility / GPR Surveys
- CCTV and drainage surveys