The project involved intervention at six key areas in Scotland ranging from Heavy S&C refurbishment, Level Crossing design and traditional Track Tamping. This involved;
- Challenging programme required flexibility and quick mobilisation to meet requirements
- Acted as Track Design Lead
- Permanent Way Design (Form-A/B)
- Bespoke design solutions including heavy refurbishment of S&C, level crossing and platform interfaces, track tamping and localised track lowering
- From feasibility to detailed design then construction support and as-built analysis
- Last minute changes in scope were successfully incorporated into the designs without impacting construction dates
The project presented a number of engineering challenges such as;
- Installation of a new contraflexure turnout on electrified line constrained at low mileage end by a “foul clearance” bridge with substandard ballast depths and a crossover, at the high mileage end interface with Station platform
- Grounding assessment and specification of new Level Crossing components – one particular site (shown centre left) was adjacent to a platform which had existing non-compliant heights and offsets
- Ballast renewal and ironwork replacement of a turnout which extended beneath an overline structure
- Track Tamping design >1,000m delivered as a CAT 0 site which featured tie-in points adjacent to Underbridges which had failed loading assessments
Working closely with Avidrail and fostering a good working relationship with the Network Rail works delivery team to develop robust solutions in accordance with the project scope.